Jamaica News: The National Works Agency (NWA) is reporting that the foundation for the Jacob’s Hut bridge in Clarendon has been completed as part of ongoing works to repair the structure.
Senior Communications and Customer Services Officer, NWA, Ramona Lawson, told JIS News that work has intensified on the project in recent weeks, with significant concrete works planned for the next phase of construction.
“Over the next few weeks into next month, the activities on the project will concentrate on completing all the concrete works, with the construction of the side walls and the deck of the structure,” she pointed out.
Independent and Private Schools Encouraged to Register with JISA
“The project also involves sidewalk construction, the installation of guard rails, pavement works, the reinstatement of the approach roads and some amount of river training works,” Ms. Lawson added.
The bridge is located along one of the primary areas that take persons from Jacob’s Hut and Denbigh towards several communities, including Pleasant Valley, Woodside and Race Track.
The bridge collapsed due to heavy rains in May of 2017, and the NWA subsequently awarded a contract for its replacement.
Source: JIS News
NOTE: If you have a real-life experience send Mckoy’s News your CONFESSION, GOSSIP or DEAR MCKOY to mckoysnews@gmail.com we will publish. We don’t publish names and locations so your personal information will be protected. Send us now!!!!!
© 2019 http://www.mckoysnews.com. All Rights Reserved.
All material and other digital content on http://www.mckoysnews.com may not be reproduced, published, broadcasted, rewritten or redistributed in whole or in part without prior express written permission from Mckoy’s News http://www.mckoysnews.com